Prompt Payment – What Do Owners and Generals Have the Right to Withhold?
July 21, 2017 Leave a comment
A Forum on Key Legal Issues for Design Professionals, Contractors, and Developers
July 21, 2017 Leave a comment
Under California Civil Code section 8814, if a direct contractor has withheld a retention from a subcontractor, the direct contractor must pay the subcontractor the retention amount within 10 days of receiving a retention payment, unless a “good faith dispute exists between the direct contractor and the subcontractor.” In turn, section 8818 provides that if an owner or direct contractor does not make retention payments as required by section 8814, then the owner or direct contractor is liable for a penalty of 2 percent per month on the amount wrongfully withheld.
So what then constitutes a “good faith dispute?” Under Martin Bros. Constr. Inc. v. Thompson Pacific (2009) 179 Cal.App.4th 1401, a “good faith dispute” for private projects included both contract price disputes and change order disputes; however, in East West Bank v. Rio Sch. Distr. (2015) 235 Cal.App.4th 742, the Court of Appeals held that a “good faith dispute” in a public project did not extend to disputes over change orders. Once the legitimate purpose for retaining the funds ends, the public entity must release the funds or suffer the statutory penalties.
Seems straightforward enough, right? On private projects, a good faith dispute means contract price disputes and change order disputes, on public projects it only means contract price disputes.
Enter United Riggers & Erectors v. Coast Iron & Steel, Co. (2015) 243 Cal.App.4th 151, which extends the East West Bank decision from the public works context to private projects. In the matter, Coast Iron withheld retention from United Riggers for claimed additional change order costs and damages related to mismanagement. The trial court found in favor of Coast Iron, citing Martin Bros.; however, the Court of Appeals reversed, citing East West Bank, holding that allowing Coast Iron to withhold retention when there was no dispute that it was owed (under the contract) would “unduly increase the leverage of owners and primary contractors over smaller contractors and subcontractors by discouraging subcontractors from making legitimate claims for fear of delaying the retention payment.”
In March of last year, the California Supreme Court granted Coast Iron’s petition for review. Brief were submitted July 2016.
The take-away – The law, as it stands right now is: On private projects, a good faith dispute means contract price disputes and change order disputes, on public projects it only means contract price disputes. Of course, that may change once the Supreme Court rules on United Rigger. Stay tuned!