California Appellate Court Strictly Construes Time Limits Set Forth in Right to Repair Act (SB 800)
February 14, 2017 Leave a comment
A Forum on Key Legal Issues for Design Professionals, Contractors, and Developers
February 14, 2017 Leave a comment
The Fourth Appellate District of the California Court of Appeal in Blanchette v. Superior Court (GHA Enterprises et al.) 2017 DJDAR 1302, ruled that the time limits set out in the Right to Repair Act (California Civil Code section 895 et seq.) are intended to be strictly construed. As such, the service of a proper notice under the Right to Repair Act (“the Act”) triggers the builder’s 14 day response time. Moreover, a builder’s failure to timely respond to such a notice relieves a homeowner from complying with the requirements set forth in the Act.
In Blanchette, the claimants/homeowners served a Notice of Claim on the builder. The builder acknowledged receipt of the claim 21 days after service (Civil Code section 913 requires that the builder acknowledge receipt of the claim within 14 days.) In its acknowledgement, the builder stated that the defects claimed in the notice lacked the requisite detail as required by Civil Code section 910. Additionally, the builder requested inspection per the Act. Following receipt of the acknowledgement, the claimants asserted that the builder’s acknowledgement was untimely, and subsequently filed a complaint in Imperial County Superior Court. The builder successfully moved to stay the proceeding pending compliance with the Act. The homeowners petitioned for a writ of mandate following the trial Court’s order to stay the action.
The writ requested that the Fourth District vacate the order staying the action because the homeowners’ compliance with the Act was relieved due to the builder’s failure to timely acknowledge receipt of the claim. The Fourth District agreed with the homeowners. The Fourth District reasoned that the builders’ untimely response is contrary to the Act’s goal of promptly resolving claims without litigation. This goal cannot be achieved by permitting builders the serve untimely responses.
The Fourth District considered whether the lack of specificity in the notice of claim impacts the builder’s response obligations. After consideration, the Court determines that the Act sets out minimum requirements for the notice of claim notably: name, address and a statement of the alleged violations. Proper service of the notice of claim then triggers the 14 day response time. The Court expands that if the builder believes that the statement of the alleged violations is insufficient, the builder should raise the issue in its acknowledgment. As such, the purported lack of specificity in the claim is not grounds to ignore the notice.
The Blanchette decision confirms that the timelines set out in the Right to Repair Act are to be strictly construed. Failure to comply with the timelines in the Act, absent agreement among the parties, will likely relieve compliance with the remainder of the Act. As seen here, if the builder believes that there are deficiencies in the notice of claim, it is important for the builder to keep the time constraints in mind in order to avoid a waiver argument.